Fundraising As Of 3.1.25
-
Estimated Construction Costs: $4,200,000
-
2025 Cash Pledged for Construction Costs: $200,000
-
Estimated In-Kind Donations (including land): $3,000,000
-
Estimated Construction Loan from BankWest: $1,200,000
-
Cash or In-Kind Donations Still Needed: $500,000

Week of October 21, 2024 Phase 1
Tyler Gearin from Gearin Outdoor Services began the work of clearing the trees and brush before the land was leveled.
Doboszenski & Sons, Inc. began leveling with their equipment to prepare the land for Phase 2 on a bright and crisp morning.
In the hallways of Rockford Area Schools, there was a buzz as faculty & students spoke of the progress being made. They are eager for construction to begin.
​
​
​

Ground Breaking
​
Phase I (clearing and grading the land) Groundbreaking to start on 10.21.24
​
We are still actively fundraising to meet the above goal and begin construction in 2025.
Check out our GoFundMe campaign here to learn more and help build the ROCK!
Drawings
​
Modern Interior Design
​
-
Assembly hall
-
Food service area
-
Student Lounge
-
Counseling Offices
-
Catering Kitchen





Thank you to Partners
and Donated Services!
-
Architect: MohagenHanson
-
General Contractor: Ebert Companies
-
Marketing/Design Team: KLN Family Brands
-
Office Space: BankWest
-
Website: Rev Branding
-
Environmental Services: Haugo Geo
Technical Services
-
Survey: Otto Associates
-
Land Clearing: Gearin Outdoor Services
-
Land Excavating: Doboszenski & Sons